MnDOT releases St. Croix bridge report
Go Deeper.
Create an account or log in to save stories.
Like this?
Thanks for liking this story! We have added it to a list of your favorite stories.
MnDOT today released its St. Croix River Crossing project annual report. The report details what the Minnesota and Wisconsin transportation departments have completed or are working on related to what will be the state's largest bridge project over the past year.
And it gives a preview of what to expect.
This month, engineers are working on preparing to let contracts for the bridge's river foundations, and for the bridge superstructure this fall.
Turn Up Your Support
MPR News helps you turn down the noise and build shared understanding. Turn up your support for this public resource and keep trusted journalism accessible to all.
The report provides a breakdown of preliminary estimated construction costs:
Minnesota Roadway Approach $60 million
River Bridge Early Foundation $45 million
River Bridge and Ramp Bridges $255 million
Wisconsin Roadway Approach $40 million
Subtotal: $400 million
Construction is expected to begin on the Minnesota roadway approach in April. Foundation work is expected to start in May. Work on the project is expected to continue through 2017.
Here's the timetable:
MN Roadway: 2013 to 2014
Foundations for new river bridge: 2013
New river bridge and ramp bridges: 2013-2016
WI Roadways: 2014-2016
Lift Bridge Conversion Project: 2017
Mitigation Package Implementation - ongoing to 2017
Check out the report here.