Cost rises for Fargo-Moorhead flood diversion project
Go Deeper.
Create an account or log in to save stories.
Like this?
Thanks for liking this story! We have added it to a list of your favorite stories.
There's a new, higher price tag for the Fargo-Moorhead flood diversion project.
A new consultants report puts the cost at $2.1 billion, up from a 2011 estimate of $1.8 billion.
Construction and land costs are primary reasons for the increase.
The federal government will pay $450 million of the project cost. The remaining $1.65 billion will be shared by state and local governments.
Turn Up Your Support
MPR News helps you turn down the noise and build shared understanding. Turn up your support for this public resource and keep trusted journalism accessible to all.
A financial plan to pay for the diversion will be finalized in about a month.
Martin Nicholson with the engineering firm CH2M reminded local officials the cost could change again.
"You know, the purpose of a cost estimate in our budgeting process is to allow the diversion authority to make reasonable and prudent decisions about a finance plan long term," he said.
Nicholson says there will be some savings from building the diversion with a public-private partnership.
Construction could start later this year pending a Minnesota environmental review and permits.